The decision to abandon the Dhaka Airport-Gazipur Bus Rapid Transit (BRT) project, 14 years after it was undertaken, is an example of how public money can be wasted through flawed development planning. The cabinet at its meeting on October 18, with Prime Minister Tarique Rahman in the chair, reportedly decided to convert the 20-kilometre corridor into an ordinary six-lane highway. The decision followed a technical review by experts from Bangladesh University of Engineering and Technology (BUET), who identified critical faults in the BRT’s design and questioned its operational viability. Notably, the project originally approved in 2012 at an estimated cost of Tk20.38 billion, saw its cost more than doubled to Tk42.86 billion following repeated revisions. And, after spending over Tk28 billion, those in charge could complete 97 per cent of the civil works without a single BRT bus beginning operation. One wonders what purpose such massive spending has served other than making life miserable for the thousands of daily commuters.
The project’s fate, however, cannot be explained away merely as an engineering blunder. As reports go, inadequate feasibility studies, faulty design, poor coordination among implementing agencies and questionable procurement decisions continued to plague the work from the beginning. Worse yet, construction proceeded without even ensuring the minimum safety of people travelling along this important national highway. In one horrific accident at Uttara, a girder falling from a crane crushed a car, killing five people. But those behind such tragedies were never made accountable. The project’s repeated delays and cost escalations under the previous Sheikh Hasina-led Awami League regime speak volumes about the culture of impunity and corruption of that period. The extent of plundering project resources by implementing officials, contractors and their political patrons during that period would require an independent investigation rather than being left to speculation.
Against this backdrop, the BUET team’s recommendation to stop spending more money on a defective BRT system makes economic sense. For demolishing all the structures and building a new highway would require yet more billions of taka from an already hard-pressed exchequer. In that case, retaining the usable parts of the existing infrastructure, removing BRT stations and lane dividers and upgrading the two-lane overpasses to four lanes may be the more pragmatic option. Accordingly, Dhaka Bus Rapid Transit PLC is to be closed and the corridor handed to the Roads and Highways Division. However, one cannot claim that the decision has satisfied every concerned quarter. Some professional and academic bodies, however, have protested against scrapping the BRT project arguing that it could still be made operational with a relatively modest additional investment. Their concern is that opening dedicated lanes to ordinary traffic might eventually worsen congestion and pollution.
The disagreement, seemingly, is not just about saving a failed project or building a wider road. It rather concerns the future of public transport for the industrial city of Gazipur and the many low- and fixed-income commuters who cannot afford private cars. So, before proceeding with the conversion, the government might well make public the BUET review and a comparative assessment of the alternatives. In a similar vein, the question of developing a commuter rail service between Gazipur and central Dhaka deserves serious consideration. However, no technical solution can compensate for absence of accountability in handling public resources. The departments responsible for approving, designing and executing the BRT owe the nation an explanation why such serious flaws were allowed to dog the project for more than a decade. Any corruption, including political patronage, should invite legal action and recovery of misappropriated funds. The government must ensure that the new highway does not become another monument to the country’s notoriously wasteful project implementation culture.
Source: https://thefinancialexpress.com.bd/editorial/lesson-from-dhaka-gazipur-brt-fiasco